Iron Mountain Quarry Information - Need to act by 1/19/12
THE GOOD NEWS.
The attached SEPA
comment letter states “WSDOT
has determined that
the proposed Iron
Mountain
Quarry
will
have
a
significant
adverse
traffic impact
of SR
104”.
This is a big step forward; your SEPA comments late last month
are being heard and are effective!
THE
BAD NEWS. The
attached letter goes on to say “WSDOT
also requests these
improvements
be conditioned
to
be designed, constructed,
and
operational
within
one
year
after mining production
first starts at IMQ”.
In other words, IMQ is allowed to start and operate without a
guarantee that they will fulfill their traffic mitigation
obligation.
If you fully trust IMQ and Pope Resources, then do
nothing.
If your trust is limited, request a completion bond
from IMQ, which is commonplace in the construction industry. You can do this
by contacting the relevant State and County Officials using the email below.
NUMBERS COUNT AND TIMING IS CRITICAL,
so start a new email
NOW
and add the following by copy and paste:
1
In
the “To” line insert:
hammonp@wsdot.wa.gov;
jeffbocc@co.jefferson.wa.us;
2
.
In
the “Cc” line insert:
SeversD@wsdot.wa.gov;
dwjohnson@co.jefferson.wa.us;
3
.
In
the “Subject” line insert:
Bond to Guarantee IMQ Traffic Improvement Compliance
4
.
In
the text area insert the following text:
Dear Sirs,
Port Ludlow residents profoundly share WSDOT’s
concern about SR-104 safety hazards created by the New Shine Quarry and
sincerely appreciate that WSDOT has taken a firm technical position in their
email Severson to Johnson dated January 10, 2012.
However, SEPA and resulting permits do not normally
provide a simple mechanism to ensure that the mitigation is readily
enforceable. Our experiences with and information about IMQ raise serious
doubts concerning IMQ’s good faith. We therefore request that the State and
County take appropriate action to require that an IMQ “time and performance”
bond or its full equivalent be in place before the final permits are issued.
The cost of a time and performance bond should not be an onerous imposition.
Thank you,
5
.
At
the end, add your name and address.
6
.
You
can change and customize the email as you wish.
7
.
SEND
Do not
delay your email—the deadline is next Thursday, January 19, 2012
If you wish, you can also send the text by
USPS to:
|
Paula J. Hammond |
Board of County Commissioners |
Dale C. Severson, P .E. |
David W. Johnson |
Click Here to see SEPA comment letter.
|
FY 2012 SBCA Budget |
Lawyer Opinion Letter November 2, 2011
|
| SBCA Board | Responsibilities |
| President - Pat Traci | Overall organization and coordination | |
| Vice President - Sharon Walker | ARC Liaison | |
| Secretary - Sue Oemichen | Meeting records, minutes, correspondence | |
| Treasurer - Chris Whitehurst | Budget, Finances, Reserve Fund | |
| Asst: Treasurer - Ken Thomas | ||
| At Large - Richard Grieves | ||
| At Large - Tom Claudson | ARC Liaison | |
Architectural
Review Committee
ARC Members - Bill Centobene, Tom Claudson, Brett Oemichen, Bill Stoner,
Sharon Walker
Tennis Committee
Facilities & Long Range Planning Committee
F&LRPC Members - Dave Armitage, Mike Morgan, Chris Whitehurst
Iron Mountain Committee
IMC
Members - Dan Meade
Drainage Committee
DC Members - Tom McCay
SBCA Political Sign Policy
All SBCA monthly meetings are open to SBCA members
Minutes are available for review by SBCA members, click here
Board meetings are held on the first Friday of every month
· Staff
Linda Colasurdo, Operations Manager
Marie Brown
Heather UllmannMelinie PerryLaura KockerEvan Olson
Contact Webmaster